Here I will tell you some things about the test of coking tower.
1. Before the pressure test, the fastening bolts of the connecting parts of the pressure vessel shall be fully assembled and fastened properly;
2. At least two calibrated pressure gauges shall be used for the test, and the test pressure gauges shall be installed at the top of the test pressure vessel for easy observation;
3. Before the pressure test, the pressure vessel welding temporary pressure components, should take appropriate measures to ensure its strength and safety;
4. Pressure test site should have a reliable security measures, and through the unit technical person in charge and safety management departments to check and approve.
Knowing this test of coking tower, you can handle with it successfully.